Outdoor Kitchen progress


July 6, 2012


June 5, 2010


May 23, 2010, Grill chimney complete



March 7, 2010, Pizza Time!



March 7, 2010, stucco complete!



March 7, 2010, 16 cubic feet of perlite only filled it about half way.



March 6, 2010, papered, trimmed, cased, lathed, and scratch-coated.



March 6, 2010, Chimney cap placed, first pass finishing.



February 28, 2010, house and roof framing done.



February 21, 2010, from the side.


February 21, 2010, face form stripped, just starting to hard trowel it.


February 21, 2010, chimney run up a couple of courses. It will go up 5 more.


February 21, 2010, Oven face topped out.


February 21, 2010, Placed the concrete for the entry way, check out that 3rd world form work.


February 17, 2010, smoke chamber insulated, chimney base formed.


February 13, 2010, most of the face complete, smoke chamber complete.


February 6, 2010, outer arch complete (click on picture for details of smoke chamber).


February 1, 2010, inner arch complete (click on picture for detail of keyed installation).


January 30, 2010, watertable poured, forms stripped.


January 24, 2010, end brick in place (dryfitted).


January 24, 2010, forms stripped.


January 23, 2010, vault complete (click photo for more in-progress pics).


January 19, 2010, design layout.


January 18, 2010, fire brick floor placed.


January 17, 2010, slabs placed, insulating concrete placed.


January 17, 2010, ready for placement of (cut to fit) 30"x30"x3" slabs.


December 26, 2009, counter and oven bases complete.


December 18, 2009, work continues.


November 21, 2009, work begins on countertops and oven base.


November 11, 2009, pavers, foundations, and pergola poles complete.


April 10, 2009, stucco complete.


March 16, 2009, paper, lath, and trim installed.


March 15, 2009, rotten siding replaced, trim removed.